|
AN
ISLAND OF TUNNELS
Focus on a booming business
in Madeira
On
the volcanic island of Madeira, located in the Atlantic Ocean
545 kilometres from the coast of north Africa, mountains plunge
from 1,800 metres into deep valleys. Roads are tortuous and often
dangerous - which is why tunnelling is a booming business.
Travelling the old roads of
the beautiful Portuguese island of Madeira is fraught with problems.
Inland routes are slow and winding and steep cliffs tower over
the oceanside roads, bringing rock falls caused by floods from
the mountains in winter.
The answer to these
problems has proved to be tunnelling and the Via Rapida road from
the airport to the capital Funchal is a typical example. Most
of it runs over bridges and through 22 tunnels - with a further
six to be constructed - and the efficiency and beauty of the route
is a tribute to the expertise of the contractors.
Atlas Copco's tunnelling
equipment is in frequent use on the island and two Boomer drill
rigs, a 104 and a 135, will be used on the new Via Rapida tunnels
by three contractors - Zagope, Tamega and Avelino Farinha &
Agrela.
A total of 11
Boomer rigs are being used on nine current tunnelling projects
in Madeira and Atlas Copco Swellex rock bolts are also a favourite
reinforcement method in the typical volcanic basalt and tuff mix
of rock.
| Tecnorocha
President António dos Santos Lopes: His company has
built 40 tunnels in Madeira. |
 |
Mining & Construction
reports on three of the ongoing projects, all of them progressing
according to schedule with the help of Atlas Copco equipment and
expertise.
Dangerous
route
The Porto Moniz
project near São Vicente consists of five tunnels up to
1,269 metres long. From the end of 1999, it will divert heavy
traffic from the scenic coastal road that runs under the cliffs
by the ocean - a dangerous route because of rock falls and floods.
The Portuguese
contractor Tecnorocha is using three of their fleet of nine Atlas
Copco Boomer drill rigs equipped with COP 1238 rock drills - a
Boomer 281, a 132 and a 170. Blastholes are 4.2 m deep and the
advance varies between 3.5 and 4 m per blast, resulting in 7 m
per 24 hours.
Standard Swellex
rock bolts, together with mesh and shotcrete, provide permanent
support and Engineer Miguel Gouveia says: "We use Swellex
bolts because they have proved to be the most cost-effective solution.
They enable us to finish our project sooner and utilize our equipment
more efficiently."
 |
Miguel
Gouveia on the Porto Moniz project: "Swellex bolts are
the most cost-effective
solution." |
The Ecumeada Tunnel, being
built through the Serra de Agua mountain in the centre of the
island, will be 3.1 km long when it opens in November, 2000. It
will be Portugal's longest tunnel and is expected to cut driving
time from the north to the south coast by 20 minutes - and make
it a much safer journey.
Contractor EPOS
is tunnelling by drill and blast, using Standard Swellex rock
bolts together with steel fibre reinforced shotcrete when the
rock is good enough and steel arches together with wire mesh and
shotcrete when it is not.
The volcanic rock
formations can change very quickly and heavy water inflows are
often experienced. Says Geotechnical Engineer Luis Santos: "Swellex
bolts are very quick and easy to install and, in these constantly-changing
conditions, they give a very good anchoring effect."
Water
inflows
Ponta do Sol is
a project which consists of three road tunnels with a total length
of 1,900 metres. Today, the road runs close to the ocean through
old tunnels with smaller cross-sections than the 66 m2 designated
for most new tunnels on the island. A recent 4,000 m3 rock fall
stopped construction temporarily - fortunately, without injuries.
| Bolting
performance with the Boomer 352: Fifteen bolts per hour with
the pneumatic Swellex pump and up to 30 bolts per hour with
the hydraulic pump.
|
 |
Avelino Farinha
& Agrela are using an Atlas Copco Boomer 352 for drilling
the blast and bolt holes and very large water inflows are being
dealt with by rock reinforcement involving Swellex rock bolts
and wire mesh and shotcrete, followed by the application of a
waterproof plastic sheet before the final 25 cm-thick, cast-in-place
lining is made.
The heads of all
bolts are cut away to get an even surface before the plastic sheet
is installed.
|