MAKING WAY FOR A NEW GENERATION!

A more productive successor will replace an old hydro power plant

The tiny Fløyrli hydro power plant, tucked away neatly at the foot of towering cliffs in a remote Norwegian paradise of fjords and mountains, has spent the last 80 years doing its job efficiently. Now it's time to take a new generation of power-producing technology underground.

Early this century, Norway started harnessing the vast potential of its countless high-altitude lakes to generate hydro electric power.

Dozens of low-capacity generating plants were installed to serve the needs of a small population scattered across harsh and often inaccessible terrain.

The Rocket Boomer 353S: Coping effortlessly in the 1:5 gradient tunnels.

A typical example - and one of the oldest - is the Fløyrli plant, at the foot of the precipitous east side of the Lyse Fjord in the wild and beautiful region of south-west Norway. Built in 1917 and extended during World War II, its five generators have a total output of 27 MW and produce 166 GWh annually.

Water for the old plant is taken from lakes above the fjord - and alongside the pipeline is one of the world's longest wooden stairways. It descends 700 metres to the plant and has 4,400 steps.

No road access

The plant is owned by Lyse Kraft, the fourth-largest power producer in the country, which has decided to close the outdated facility and replace it with a more efficient, twin-generator installation of 160 MW, boosting production to 300 GWh without increasing water consumption. Another factor is that new environmental legislation from 2006 will outlaw surface pipelines like the one at the site.

Construction of the new power station is being carried out by Selmer, Norway's biggest contractor. There is no direct road access from the site and transportation of equipment and materials is by helicopter - one of the drill rigs was airlifted - or by ferry, using a heavy-duty quay which Selmer had to install before the project could start. The quay has an adjustable ramp to cope with the tidal waters of the fjord, which connects to the North Sea at Stavanger.

Tight team: Deputy Site Manager Eirik Moe (left) with Vegard Halden, Atlas Copco Sales Engineer.

Tunnelling at the project is all drill and blast and involves a 2,200 m-long spiral road tunnel with a 1:5 gradient and a cross-section of 27.5 m2, a 1,500 m-long pressure tunnel with the same incline and cross-section, and a 280 m-long, 20 m2, headrace tunnel. There is also a 16.8 m2 pressure shaft, 412 m deep, on which hand-held drills and a raise lift will be used. The power house excavation is now complete.

Total excavation for the tunnels and turbine halls is 170,000 m3 - all of which is being tipped into the fjord. The composition of the rock is identical to the glacial scree that falls into the fjord daily.

Men and machines

There are 35 tunnellers and a drill rig fleet of three Atlas Copco jumbos at the site - Selmer is a long-time user of Atlas Copco equipment. The tunnellers work two weeks on, one week off, with two 10-hour shifts per day, six days per week.

The fleet comprises: A new Rocket Boomer 353S with three drilling booms, and COP 1838 rock drills on 18-ft feeds; a three-boom Rocket Boomer H 188, upgraded with COP 1838 rock drills on 18-ft feeds; and a 20-year-old Boomer H 115 with two booms fitted with COP 1032 rock drills on 12-ft feeds.

Atlas Copco Rock Tools drill steel equipment is used throughout and rounds are drilled to a depth of 5.1 m. Each round includes 62 blastholes of 45mm and four 102 mm centre holes, drilled with Atlas Copco's new R 35 Enduro drifter equipment (see Products & Progress, Page 17). The tunnellers are achieving an advance of 4.7-5.1 m per round.

Inside the control room: Newer technology will soon be replacing the old Fløyrli hydro power station.

However, varying rock conditions and water-logged fissured zones have caused some problems, says Eirik Moe, Deputy Site Manager. These include difficulties in charging the holes and the need for considerable grout injection to seal against water leaks with a pressure of 35 bar.

There have also been considerable rock bursts. Extensive shotcreting and bolting is being carried out in the weak zones, using resin-grouted rebars 2.4 and 4 m long.

Face to face

The pressure tunnel is being driven with the old Rocket Boomer H 188 and 600 m has been completed so far. High speed drilling is necessary to reach the point where access is gained to begin work on the pressure shaft. The Boomer H 115 has started the headrace tunnel, having finished the access tunnel, and the Rocket Boomer 353 S has reached the 650 m mark in the spiral road tunnel.

Shift boss and rig operator Erik Saltvik, a driller for 21 years, switches from face to face to work with two of the Boomer rigs - the 188 and the 353. He says: "I like the old 188 very much. I've handled it from day one and there have been no real problems with it. It's an extremely reliable rig which performs well.

"In fact, it drills as well as the new 353 which we got in May, one reason being that the 188 is equipped with the modern COP 1838 rock drills. But the 353 is a good rig, as you would expect. A big difference is the cabin, which makes working with the rig so much more comfortable."

Lifeline to the outside world: With no road access, transportation for men and materials is by boat or helicopter.

Erik Saltvik is also a fan of Atlas Copco's rock drills. "When I started in the job, I was using Atlas Copco's first hydraulic drill - the COP 1038, which I liked a lot. Its successors, the COP 1238 and the 1440, were even better.

"But the COP 1838 is outstanding. It's not only fast - it can go much longer between overhauls and it's kind to the drill steel. I can drill up to 75 metres between regrindings, and our average drilling speed is 2.20 metres per minute."

Tough challenges

Workshop Manager Vidar Sundquist has been with Selmer for 24 years and says: "I've learned to appreciate Atlas Copco drilling equipment - it's reliable and easy to work with. The old Rocket Boomer 188 has long been a favourite, especially after I fitted the COP 1838 rock drills.

"However, I'm convinced that the new rig will come out on top once we've got a grip on its new technology and learned how to get the best out of it. It has great advantages, such as the comfortable cabin, excellent traction and high braking power - all of which are a considerable help in these one-in-five gradient tunnels.

"This project has, in fact, the steepest gradients I've ever come across."

And that is just one of the many tough challenges in the construction of the new power station, which is due to come on stream in January, 1999.

 

 

Top