|
WALTZING
HOME AHEAD OF SCHEDULE
Austrian tunnellers beat
the clock on town by-pass project
Austria
and tunnels go together like Strauss and Viennese waltzes. The
country's tunnellers, using innovative techniques and the best
equipment, have a history of recording world-class performances
- such as cruising to completion two months early on a recent
project.
The New Austrian Tunnelling
Method (NATM), developed between 1957 and 1965, put the country
firmly at the forefront of tunnelling development.
The technique
- largely based on exploiting the natural load-bearing capacity
of rock and using a variety of swift and effective support measures,
according to the type and quality of the rock - quickly became
the standard for tunnelling excellence worldwide.
Now an increasing
number of beautiful towns and villages in mountainous Austria
are being by-passed by tunnels to reduce traffic congestion, noise,
fumes and pollution of the alpine air.
These tunnels
are built with the quick and sure expertise accumulated by experience.
A current example is the Schönberg tunnel, about 40 minutes
drive from Salzburg, which was started in February last year and
completed in April this year - a comfortable two months ahead
of its scheduled completion date.
Traffic diversion
Just under three kilometres
long, the tunnel is part of a USD 60 million traffic-diversion
project around the town of Schwarzach, on the road between Bischofshofen
and Zell am See.
The companies
involved in the joint venture, Vienna-based Stuag and Universale
Bau of Salzburg, are two of the best-known and experienced long-distance
tunnelling operators in Austria.
 |
Site
Manager Helmut Lutz,
of the Stuag company:
"We've been using Atlas Copco drill rigs almost exclusively
for the past10 years." |
For them, the rapid drilling
work was a result of favourable rock conditions and two new Atlas
Copco Rocket Boomer drill rigs, a three-boom 353S model and a
two-boom 352S unit, both equipped with COP 1838 rock drills. The
two machines were rented with an option to buy.
For the book-keepers,
the relatively uncomplicated and precise drilling meant little
or no cost overruns. And for Atlas Copco the successful project
was solid confirmation that the equipment more than met the challenge.
Reasonable rock
The rock, although poor by
international standards, is considered reasonable for Alpine conditions,
consisting of various forms of highly-fractured phyllites, mixed
with green shale.
Says Site Manager
Helmut Lutz of Stuag: "We were able to drill an average of
6.6 rounds a day with one round equal to a length of between 1.6
and 2.2 metres, depending on the conditions. We had set ourselves
a goal of four to five rounds a day."
The area through
which the tunnel passes is familiar ground for Mr Lutz. He worked
on a railway tunnel project not far from the latest site and he
knew what to expect in terms of rock type and formation.
"We were
also familiar with Atlas Copco machines," he continues. "We've
been using them almost exclusively for the past 10 years. If we'd
changed to different products, it would have taken time for our
mechanics and operators to get acquainted with them.
"We're used
to not having problems - and that was one of the major reasons
for staying with Atlas Copco, even though there were some attractive
competitive bids. We trusted Atlas Copco's ability to fulfil the
contract."
And the combination
of equipment quality, reliability, high capacity and good service
enabled the drillers to finish two months ahead of schedule, working
three eight-hour shifts per day.
Keeping costs down
Keeping costs down was an
important part of the project and Mr Lutz continues: "We
managed to keep within the budget by hiring experienced crews,
by good preparation and by using new equipment which meant fewer
mechanical problems and maximum availability."
The cost factor
was one reason the contractor decided to rent the best rigs available
and both rigs have now been bought by the companies. Universale
Bau has the three-boom rig and the two-boom rig is to be bought
by Stuag.
| Star
performer leaves the tunnel: Lights ablaze, one of the Boomer
rigs comes out through the east portal. |
 |
For Mechanical Foreman Johann
Lerner of Universale, the most important aspect for his servicing
crew was the fact that his mechanics had all worked with Atlas
Copco rigs before. "The main advantage was the uncomplicated
operation and the quick provision of spare parts," he says.
Praising the co-operation
with Atlas Copco service representatives, he pointed out: "Someone
was on call 24 hours a day, seven days a week, and there were
monthly equipment checks."
Easy servicing
Mechanic Franz Seidl says
he liked the Boomer rigs for their relatively easy servicing intervals.
"Normally we brought them in for servicing after 400 operating
hours. That's about 80,000 drill metres. This tunnel involved
about 500,000 drill metres."
Excavation Foreman
Joseph Lederer, of Universale Bau, said that one of the most important
features on the three-boom rig was the raiseable cab.
"This gives
the operator a better view of the drilling direction in the roof
section. A better view means less overbreak and lower costs when
applying the concrete lining."
The two Rocket
Boomer rigs were also the first generation of electronically-controlled
machines. The operator has to use only three joysticks instead
of the standard forest of levers. Two joysticks position the booms
and a further controls the drilling.
The rigs were
operated entirely manually with a drilling pattern consisting
of 80 to 100 holes 45 mm in diameter, depending on the properties
of the rock. The contour holes were placed at a maximum spacing
of 30 cm.
 |
Co-operation
and teamwork during the project: From left, Mechanical Foreman
Johann Lerner, Mechanic Franz Seidl and Atlas Copco's Peter
Aigner with the Rocket Boomer 353S drill rig. |
Another important contribution
to the low cost and rapid completion of the drilling operation
was the decision to use Atlas Copco's four-metre-long Super Swellex
bolts to reinforce the roof. Helmut Lutz says these were quick
to install and extremely reliable.
All the rock bolts
used in this operation were Super Swellex from Atlas Copco, as
were 60% of those used in the side walls. Other reinforcement
methods included the installation of wire mesh, steel arches and
shotcreting. The whole tunnel will be concrete lined.
First choice
Swellex is now rapidly becoming
the first choice for designers and contractors using the NATM
technique, replacing the more traditional grouted rebars.
Rock bolts are
fundamental for stabilizing the rock mass between the excavation
phase and final lining. Therefore, NATM requires bolts that are
not only reliable, easy and fast to install, but which also give
immediate support along their whole length and in a wide range
of rock.
Atlas Copco representative
Peter Aigner says the Schönberg project is also a good example
of how contacts between the supplier and the contractor can be
strengthened, both professionally and personally.
"Both sides
knew that they were confronted with tough market conditions but
we tried to treat each other in the fairest way possible,"
he says.
|