|
Bajar
versión española
Carrera contra las lluvias
en PDF (749kb)
 |
| Clearing
up underground: An Atlas Copco Wagner Scooptram ST-7.5Z carries
out its work in a tunnel at the San Roque project in the Philippines. |
Dam
project speeds ahead
to beat the typhoon season

RACE
AGAINST
THE RAINS

A large fleet
of Atlas Copco underground vehicles is winning high praise for
its performance on a multi-purpose dam project in the Philippines.
The fleet played a vital role in putting the project back on schedule
after precious time was lost last year when typhoons caused disastrous
flooding at the site.
The 22 Atlas
Copco Wagner trucks and loaders were temporarily diverted from
their main task of loading and hauling blasted rock to the more
urgent job of removing flood silt so tunnelling could continue.
Now the fleet is working at top speed to make the site flood-proof
before this year's typhoon season starts.
 |
Thurlo
Hooper, R.E.O.L.'s deputy site construction manager: "The
high availability of the Atlas Copco Wagner equipment has
helped us to make up the time lost from last year's setback." |
Thurlo
Hooper, Deputy Site Construction Manager for the US contractor
Raytheon Ebasco Overseas Ltd. (R.E.O.L.), says: "We've got
to have the main upstream cofferdam construction up to an initial
height of 23 metres and complete two diversion tunnels before
the summer rainy season starts. When the river rises, the high
water will flow through the two tunnels - otherwise we could lose
the cofferdam.
"The
Wagner equipment has performed real well, and we're very happy
with it. Its high availability has helped us to make up the time
lost from last year's setback."
Vast reservoir
The USD 1.19
billion San Roque dam project is located on the River Agno in
the Cordillera Mountains of Pangasinan province, about 250 km
north of Manila, the Philippine capital.
The massive dam is believed to be the biggest in Asia and is the
twelfth largest in the world. It will create a vast 14 km2 reservoir
for recreation, provide downstream irrigation to 87 km2 of farmland
and supply power to the national grid from the dam's integral
345MW hydro-electric power station.
About 45M
m3 of graded and processed material will go into the 188 m-high
main embankment, which has a crest length of around 1,100 m. R.E.O.L.
is working two shifts around the clock, seven days a week, to
build the huge embankment at the rate of 4,000 m3/h of material
delivered by dump trucks.
But the top
priority is to complete the remaining two flood diversion tunnels
- the first and smallest of three tunnels was ready in March and
diverted the river so that work on the upstream cofferdam could
start.
The three
diversion tunnels have been designed to accommodate a flood flow
of 4,600 m3/sec. The two largest high-level tunnels are 16.5 m
high, 11 m wide and horseshoe-shaped. They will each cater to
flows up to 2,100 m3/sec. The remaining 400 m3/sec of flood water
will go through the smallest low-level tunnel, which is 817 m
long, 6m x 6m and also horseshoe-shaped. It will normally have
a flow of about 120 m3/sec.
Cadillac
of tunnelling
 |
R.E.O.L.'s
General Equipment Manager Don Johnson: "Atlas Copco Wagner
vehicles are the Cadillacs of tunnelling, and we have what
is probably the world's finest fleet at San Roque." |
The Atlas Copco
fleet comprises 22 versatile, underground, Scooptram loaders and
Mine Trucks - the first in the Philippines. Don Johnson, R.E.O.L.'s
general equipment manager, comments: "We evaluated the options
and eventually went for Atlas Copco Wagner, based on good experiences
with the equipment in the past and the fact that it was by far
the best overall package. We bought everything brand-new and we
have what is probably the finest Atlas Copco Wagner fleet in the
world at San Roque.
"For
the main tunnels, we went for six of the ST-7.5Z loaders matched
by the same number of MT-436B mine trucks. These were supported
by a further 10 of the smaller ST-2D units for use in the dam's
grout gallery tunnels. These proved too small when the size of
the tunnels was increased, so we've replaced six of them with
the larger ST-3.5 units."
Mr Johnson says he would have no hesitation in buying the same
equipment again, adding: "Wagner is undoubtedly the Cadillac
of the tunnelling industry. Everyone on site is really happy with
the exceptional availability of between 92-96% - about 13% better
than the 85% guaranteed by Atlas Copco. It's an unheard-of and
unreal availability figure - and I'm sure that the initial training
by Atlas Copco has a lot to do with it."
He says that
training and Atlas Copco Wagner's comprehensive preventative maintenance
programme, which is part of the company's on-site full service
package, is the key to the equipment's success.
Strict
servicing
The full
service contract was set up last summer by Atlas Copco Wagner
in co-operation with the local subsidiary Atlas Copco (Philippines)
Inc. The responsibility is now solely with the local company's
Maintenance Supervisor Julius Sison, who looks after the workshops,
a USD 2 million stock of spares and a team of 10 mechanics who
work two, 12-hour shifts.
He says: "We service all 22 machines in strict accordance
with Atlas Copco's recommendations. We also carry out scheduled
oil sampling of all the main reservoirs every 150 hours, which
helps to indicate any potential faults so we can repair them before
any breakdowns and loss of production can happen."
R.E.O.L.
started work at the site in April, 1998, and by the time the first
and smaller low-level tunnel was finished at the end of February
this year, the larger tunnels had progressed 1,740 m.
| Tunnel
Area Manager Kevin Miller: "Atlas Copco Wagner vehicles are
top-of-the-line and the best available. I've been using them
for more than 25 years - and I wouldn't have anything else."
|
|
"We initially
worked all six faces at once, using the ST-7.5Z units to load
the Mine Trucks in the top headings and load and haul out of the
small tunnel to dump in the trucks outside the portal," explains
Tunnel Area Manager Kevin Miller of Woodward Construction, the
U.S.-based company which is supervising tunnel construction for
R.E.O.L.
"We
work two shifts round the clock and - depending on ground conditions
and the supports, shotcrete and rockbolts required - achieve an
average advance of about seven metres per day for each face.
"We
try to get two four-metre pulls per day, each leaving a muck pile
of around 500 cubic metres, which is cleared in about two hours
by a couple of the Scooptram ST-7.5Z vehicles and two trucks.
We use a third truck when the haul gets longer."
After drilling,
blasting and mucking out, the exposed rock is sprayed with an
initial 50-75 mm-thick layer of fibre-reinforced concrete in preparation
for another Atlas Copco product - Super Swellex rock reinforcement
bolts. The bolts, up to 4-m long, are strategically placed in
the roof and walls of the headings before a second spraying of
shotcrete achieves a smooth tunnel lining 350 mm thick.
Quality control
Swellex has been
selected by the designer, Golder and Associated of Georgia, USA,
as the regular pattern bolt. This hydraulically-expanded bolt
can give immediate rock support and full column bond, and has
an excellent quality control procedure during its installation.
These features are specially important when facing soft and unstable
rock, as at San Roque. Moreover, in soft rock, reinforcement is
a bottleneck in the excavation cycle - so the contractor was pleased
with the opportunity to use a fast and trouble-free bolt like
Swellex to speed up production.
The contractor
has been removing the remaining 11 m wide, 8 m high benches in
the two large tunnels - which are on schedule for completion before
the start of the typhoon season.
On target
When
the current tunnels are completed, the Atlas Copco Wagner fleet
will be moved on to muck out two 1,500 m long tunnels at the site
- a 7 m diameter irrigation tunnel and a 9 m diameter tunnel to
the main powerhouse.
R.E.O.L.
is on target to complete the project in 2001. San Roque Power
Corporation will sell and supply electricity to the national grid
for 25 years before transferring ownership to the Philippines
National Power Corporation.
|