 |
| Stand-by
in the Schulwald tunnel: One of four Rocket Boomer 352S rigs
waits for an excavator to dig out soft rock. |

AT
EUROPE'S LONGEST CONSTRUCTION SITE

Work
is under way over the whole length of the 219 km high-speed railway
line between Cologne and Frankfurt, making it the longest construction
site in Europe.
The
joint venture ATAC/KDD, consisting of the contractors Alpine Bau,
Ilbau, Beton und Monierbau, Östu Stettin, Hinteregger &
Söhne and Thyssen Schachtbau, is responsible for a 12-km
stretch of the new rail link.
On
this section of the railway is the Schulwald twin-track tunnel,
the longest on the entire project. The rock formation in the 4.5
km-long tunnel is soft and excavators are used to dig out the
rock. Blasting is carried out only occasionally to break up the
rock for the excavators.
Rock
support
Four
Atlas Copco two-boom Rocket Boomer 352 S rigs are employed solely
on rock support work. They are equipped with 14-foot feeds and
hydraulic drill supports for extension drilling. And they use
Atlas Copco Rock Tools' R32 drill rods and 48, 51 or 57 mm bits
for drilling holes up to 12 m long.
The
rigs drill 4-6 m-long holes for spiling, in which 28 mm diameter
rebars are pushed into the holes, 3-6 m holes for the final support
rockbolts, and holes up to 12 m long for face support in poor
conditions. Availability of the rigs, which are in operation for
eight hours per shift, is more than 90%.
One
rig is used at each of the four "attack" points, which
have a daily advance of 3-5 m and the total tunnel advance is
12 m per day. The rockdrills are Atlas Copco COP 1838 units, with
R32 shanks, that produce a penetration rate of 4-5 m/min with
exceptionally low wear on the drill steel and bits. The drilling
is carried out with air-flushing and water mist, which prevents
excess water from entering the rock and adequately deals with
the dust.
Difficult
task
To
protect the tunnel from water inflows, 60-70 m-deep wells are
drilled to lower the groundwater table, 10-15 m from the tunnel.
But
it's a difficult task, as the soft rock is spongelike and is reluctant
to give up water. However, the final tunnel lining will be plastic-shielded
(installation starts next spring) for protection against water,
after which the groundwater level will return to normal.
 |
| At
the Schulwald twin-track rail tunnel: Site Manager Franz Holzfeind
listens to Atlas Copco's Karl-Heinz Wennmohs. |
Site
Manager Franz Holzfeind says: "We are very pleased with the
progress we are making with the help of the four Atlas Copco Boomer
rigs, which are coping well in the soft rock and generally poor
working conditions.
"In
the difficult area of rock bolting, they are helping us to stay
on schedule. Availability of the rigs is good, and the life of
the drilling equipment is more than satisfactory."
|