 |
| A
view of the Alte Burg site: A Rocket Boomer 353ES rig started
drilling in the 874 m-long tunnel on March 15 - and reached
the halfway point by May 6. |

CHALLENGE
OF THE TUNNELLING SITES

Germany's
new A71 highway will connect Erfurt in the former eastern sector
with Schweinfurt in Bavaria - and pass through the lovely countryside
of Thüringen.
Atlas
Copco equipment is working at three tunnelling sites on the road
and one of them is the 7.9 km-long Rennsteig tunnel, which will
be the longest road tunnel in the country.
The
contract for this tunnel, valued at DEM 430 million, was awarded
to Arge Rennsteigtunnel, a joint venture of Ed Züblin AG,
Wayss & Freytag AG and Bickhart-Bau. The project got under
way in August, 1998, and construction is expected to take 45 months.
Tunnelling
is carried out using NATM (New Austrian Tunnelling Method), with
top heading, bench and six attack points. Six Atlas Copco drill
rigs - three Rocket Boomer 353ES and three Rocket Boomer 352 units
- handle the drilling.
Main
challenge
"The
main challenge at this worksite is logistics," says Project
Manager Karl Prax, who recently celebrated his completion of 50
km of tunnelling. "It is a bottleneck and makes our work
much more demanding than the rock conditions in the excavation
of this long tunnel."
| Karl
Prax, Project Manager at Rennsteig, recently celebrated 50
km of tunnelling. He says: "Logistics are our main challenge
here." |
 |
Rock
at the tunnel site is porphyr mixed with sandstone or quartz and
has a compressive strength of 150-200 Mpa.
The
Rocket Boomer 353ES rigs, equipped with the Bever Control system,
are used to drill 120 holes (325 drillmetres per round) for blasting
at the top heading. The rigs are equipped with Atlas Copco 48
mm button bits and R38 Enduro drill rods. Drilling is done with
water flushing. After drilling the holes are blown clean with
compressed air from GA 22 screw compressors, mounted on the rig.
High
availability
Drilling
time per round is 40 minutes, penetration rate is 4 m/min and
drill bit life is described as "excellent."
The
25 drilling patterns installed in the Bever Control system make
the Rocket Boomer 353 ES rigs well prepared for all drilling conditions.
Advance per round is 2.5 m in rock classes 3 and 4.1, reducing
to 1.7 m in classes 4.2 and 4.3. The other three Atlas Copco drill
rigs - the Rocket Boomer 352 units - are used only for bolting
and probe-hole drilling.
 |
| Germany's
longest road tunnel: A Rocket Boomer 353ES drill rig is one
of six Atlas Copco Boomer units driving the 7.9 kmlong Rennsteig
road tunnel, which has twin tubes. |
There
are two Atlas Copco service containers at the worksite and the
availability of the rigs is 98%.
If
the laser-controlled profile of the tunnel is satisfactory, 3-5
cm of shotcrete is applied to the walls of the tunnel. Then steel
arches are installed, with 1.7-2.5 m spacing, depending on the
rock class. Steel mesh is then applied with another 10 cm layer
of shotcrete, followed by the installation of 4-6 m rockbolts
at the rate of seven bolts per metre of tunnel.
Karl
Prax concludes: "The fact that we have six Boomer rigs working
on this important project demonstrates the faith we have in Atlas
Copco equipment.
Availability of the rigs, at 98 per cent, could hardly be better
and the three rigs, which are equipped with computer supported
drilling, are handling all drilling conditions with few problems."
Five
rock classes
Both
tubes at the 1,058 m long Hochwald twin-tube tunnel, which are
25 m apart, are being excavated simultaneously with the same equipment.
It is being constructed by Arge Baulos Hochwald, consisting of
Heilit+Woerner Bau AG and Jäger Baugesellschaft MBH.
The
tunnel is being driven by top heading and bench with an advance
rate of 4.7m/day for the top heading and 20 m/day for the bench.
An Atlas Copco Rocket Boomer 353 Eagle with Bever Control is drilling
130 blastholes with 45 mm button bits and HEX35 drifter rods.
The
rock is granite and has a compressive strength of 150-200 Mpa.
Penetration rate is 3-4 m/min and to drill a round, including
charging, takes less than two hours.
There
are five different rock classes and the advance per round and
required rock support is specified for each one. Swellex rock
bolts are used in rock class 4 when there is a problem with water.
Otherwise cement-grouted rebar bolts are used.
| Walter
Kubick, Site Manager at Hochwald, is pleased with the performance
of the Atlas Copco equipment and his drill steel contract
with the company. |
 |
Personnel
at the site are pleased with the performance of the Atlas Copco
equipment. Site Manager Walter Kubick, from Heilit-Woerner, says:
"We have a drill steel contract with Atlas Copco which works
well. We also have an excellent relationship with Hans Lauer,
Atlas Copco's Technical Supervisor, who is a real superman. He
is always on the spot when we want him, he knows exactly what
he is doing and has never let us down."
 |
Atlas
Copco's Technical Service Manager, Hans Lauer, is described
as "a superman" for his reliability, work and support at the
Hochwald tunnel site. |
Good
performance
The
Alte Burg tunnel is the shortest on the northern side of the mountains
at 874 metres. It has twin tubes, each with a 7.5 m-wide roadway,
and is being constructed by the joint venture Arge Tunnel Alte
Burg, which comprises Schachtbau Nordhausen GmbH and Leonhard
Weiss GmbH & Co.
An
Atlas Copco Rocket Boomer 353ES equipped with COP 1838 rock drills
is being used for the excavation of the top heading. Another Rocket
Boomer 352 is employed in bolting and bench excavation and Atlas
Copco Swellex 2.7 m-long bolts are providing rock support.
 |
| A
Rocket Boomer 353 in the Alte Burg tunnel. |
With
the help of Atlas Copco 45 mm button bits, penetration rate is
4-5 m per minute and the drilling time for each 136-hole round
is between 50 and 60 minutes.
May
celebration
Site
Manager Wolfgang Löbel says: "I've been using Atlas
Copco tunnelling equipment since I started in the business with
pneumatic equipment in 1970. Everyone on the site is very satisfied
with the performance of the Rocket Boomer 353 ES rig.
"We
started drilling on March 15, and we were holding our halfway
celebration party by May 6. The availability of the rig has been
95%, and the only damage we have suffered was caused by a rockfall
and a damaged cable.
 |
Wolfgang
Löbel, Site Manager at Alte Burg, has been using Atlas Copco
equipment since 1970. |
"We're
also extremely happy with the performance of the Atlas Copco rock
drills, which have a service interval of between 50-80,000 drill
metres."
And
Mr Löbel adds that the quality and performance of the drill
bits is "excellent". The bits last some 700-1,500 metres
without regrinding and the drill rods last up to 12,000 m.
The
Rocket Boomer is equipped with a Bever Control to guide boom positioning
and log drilling results. Before tunnelling was started, operators
and maintenance crews had three weeks of training, closely followed
by software training prior to delivery of the rigs.
Total
cost of the Alte Burg tunnel is DEM 50 million and it will take
an estimated 39 months to complete.
|