 |
|
The Hitra portal: Soon to be the start of a 5.3 km undersea
journey. |
Drillers
move Hitra Froya tunnel one year ahead of schedule

Triumphant
drillers at the Hitra Froya tunnelling project in Norway raise a
glass to congratulate themselves on a job well done. They have just
achieved a breakthrough that has put the whole project one full
year ahead of schedule.

Breakthrough
at the Hitra Froya road tunnel, which runs under the sea to connect
two islands off the coast of Trondheim, was originally intended
to take place in May, 2000.
But
the drillers, using Atlas Copco equipment, have been so successful
that they were able to pull it off early, in September.
And
that has brought the opening day of the tunnel forward to Midsummer
Eve (June 23) next year - a full year ahead of the original schedule.
The plan to construct the three-lane subsea tunnel between the
mainland and the island of Hitra to replace the existing ferry
service was the subject of much discussion back in the early 1990s.
Residents
in the area feared the project would have a damaging impact on
their beautiful surroundings, both during construction and when
it came into service. They were worried about the prospect of
dramatic change and its effect on both their environment and their
lives.
But Statens Vegvesen, the Norwegian highway authority, and the
consultation committee of residents co-operated to find a solution
and agreement was finally reached. It resulted in the 5.65 km-long
tunnel being completed ahead of time and opening in 1994.
The
tunnel and its environs quickly became part of the local surroundings
- so much so that residents happily supported plans for a similar
second tunnel between Hitra and its neighbouring island Frøya.
The same team of Statens Vegvesen and the contractor Selmer got
the project under way early last year and achieved breakthrough
recently. The tunnel will link the two islands - each with a population
of 4,000 - and provide an all-weather route from Frøya
to the mainland.
Two-lane
road
The 5.3 km-long crossing is being developed from both the Hitra
and Frøya portals and 3.6 km of the tunnel is beneath the
sea. The tunnel will have a two-lane road and its cross-section
is 55m2. There will be nine niches for emergency lay-bys and three
truck turning bays.
Of
the 300,000 m3 being excavated, some 9,000 m3 is in poor ground
where 6- 8m x 32 mm rebar spiles are cement-grouted into 55- 64
mm holes drilled by the Atlas Copco Rocket Boomer 353S. The Unigrout
system equipped with thenew, user-friendly PUMPAC grout pump,
based on the same double-acting principle as the well-known ZB
range of pumps, is used for this part of the operations. The spiles
are installed over the crown in umbrellas with 2- 3 m overlap.
Radial bolting, using 2.4- 4 m-long rockbolts, is also undertaken
as required.
It
was estimated that 4,000 spiling bolts would be needed for the
whole contract, but more than double that amount has been used.
The rocks of the area are of the Precambrian era with gradual
transitions between various gneissic rocks such as granite gneiss,
micagneiss and migmatite. A few bands of limestone/marble have
also been recorded.
Poor
conditions
During final design in 1995, core drilling revealed exceptionally
poor ground conditions, which resulted in a realignment of the
proposed tunnel. Refraction seismic measurements revealed more
weakness zones than for any previous undersea tunnels constructed
in Norway. Two of the weakest zones are on the alignment and one
is in the Tarva fault, which can be followed more than 150 km
towards the north-west on the Norwegian mainland.
All
face, probe hole and rockbolt drilling has been carried out by
a single drill rig at each of the two faces. Both rigs are Atlas
Copco Rocket Boomer 353S units equipped with COP 1838 rock drills.
Using Atlas Copco Rock Tools, they drill up to 77 holes of 5m
x 51mm for a standard round - but the operator can select a variety
of patterns down to 73 holes, according to rock conditions. Other
Atlas Copco equipment used in the tunnel includes 5.5 m R35 Enduro
drill rods and 48 mm ballistic bits, type 77.
The
two rigs are equipped with systems for contour profiling and scanning
of the face. Using a single laser beam as a reference point, the
rig can be accurately positioned at the face to drill the selected
hole pattern and the operator can also decide on any trimming
holes required to tidy up the previous round. This arrangement
affords the facility for fast and accurate drilling with the minimum
number of holes, while keeping overbreak within tight limits.
 |
|
The Hitra portal: Soon to be the start of a 5.3 km undersea
journey. |
Efficient
drilling
Drilling takes approximately 75 minutes per round and five rounds
are normally drilled and blasted in each 24-hour cycle. The maximum
advance in each heading is 110 metres per week.
The
drill rigs are also equipped with RAS mechanised rod-adding systems,
which consist of a control unit and two mechanical grippers mounted
on the feed beam. All loading is carried out by excavators with
a loading rate of 600 tonnes per hour - and it takes about 45
minutes to clean up after a full round.
Drill rig operator Sigvart Bolli has a unique role in the operations
- he doubles as a loader driver and is also the shift boss!
Asked
his opinion of the Atlas Copco equipment being used at the tunnel
site, he replies: "Atlas Copco is the only drilling equipment
for me!"
Site Manager Roar Sve, who has played a leading role since 1986
in five projects involving seven tunnels, says: "Because
of the difficult conditions, this has been the most exciting project
I have been involved in.
"Ground
conditions were sometimes so poor that parts of the tunnel excavated
themselves! But overall, the project is very successful and I
am extremely pleased."
|