 |
|
Top performance: These ROC F7 rigs, using blast hole diameters
of 89 mm and 102 mm, have exceeded all expectations, helping
the project to get ahead of schedule. |
Safeguarding
Sydney's water supply

An
enormous earth-moving project 60 kilometres west of Sydney, Australia,
is underway to protect a vital dam from the possibility of a catastrophic
collapse.

The
three-year project will build a second spillway at the massive Warragamba
Dam. With a volume four times that of Sydney Harbour, the dam is
Australia's largest concrete dam and supplies 80 percent of the
water to some 4 million people in the Sydney area.
The
second spillway is needed because the dam was originally designed
to handle peak outflows of 12,700 cubic metres per second when
it was built by Sydney Water in 1960. More recent assessments
of the Probable Maximum Flood, however, suggest that peak outflow
could be over three times that level, which would overwhelm the
dam, collapse its retaining wall and send a cataclysmic torrent
of flood water crashing down the river.
Previous
solutions to the flood risk included a proposal to raise the dam's
retaining wall 23 metres, which outraged environmentalists. Not
only would upstream wilderness areas and the scenic Kowmung River
be threatened, they argued, but massive expansion of housing in
environmentally sensitive areas downstream of the dam would be
encouraged. Since the spillway project would only divert water
away from the dam, however, it would not shrink the floodplain
downstream. More land for development, therefore, would not be
created.
 |
|
The Atlas Copco crawler rigs in action, drilling up to 750
metres in a single shift. |
Artificial
channel
About 2 million cubic metres of rock will be excavated from the
area just east of the dam's retaining wall to create an open channel
beside it, which will be concrete lined. Structures known as "fuse
plugs" will be constructed at the entrance to the spillway
to prevent its operation unless a major flood event occurs.
During
a flood, the pressure of the water would cause the fuse plugs
to be breached. Flood waters would further erode the plugs, allowing
even more water to bypass the dam and exit into the Warragamba
Gorge 300 metres downstream, securing the safety of the dam -
and Sydney's water supply.
Although
the decision to build a spillway was generally applauded by environmental
groups, issues remained, including how best to preserve the wilderness
where construction is now taking place. Since some of the native
flora and fauna are considered unique to the region, the area
being used for fill material has been saved for future restoration.
Top soil and plants have been removed and will be replaced and
replanted at the conclusion of the project.
The
operation must also operate under strict rules to limit noise,
due to the proximity of residential housing. Drilling hours are
7 am to 6 pm Monday to Saturday, with no night time drilling or
blasting.
Some
96 people from 56 contractors are currently on site. The lead
contractor, Abigroup Limited, has contracted Precision Blast Hole
Drilling Pty Ltd for the drilling of blast holes. The USD 56 million,
18-month contract will be completed by September, 2000.
Strong
performance
After removing the rock in the first year of the project, up to
60,000 tonnes of concrete and 5,000 tonnes of reinforcing material
will be used to line the spillway. In the first three months,
to May 1999, Abigroup moved 10,000 cubic metres of material per
day. That figure has now climbed to 14,000 m3 and the strong performance
of Atlas Copco ROC F7 drill rigs is an integral part of this picture,
drilling up to 750 metres in a single shift.
Precision
Blast Hole Drilling purchased their first Atlas Copco surface
drill rig two years ago. The company's co-owner, Andrew Lyell,
says that the decision was initially based on the technical features
of the machine, and adds: "Since then, the performance, combined
with the technical service and support that we have received,
has more than justified our choice.
 |
|
Cabin with a view: Operator Ken Miller, at left, with Abigroup
Safety Officer Matthew Moon, appreciates the ROC F7's ergonomics,
including its increased visibility. |
"Precision
drilling, for example, is very important in minimising the possibility
of dust and rock falling into the water supply. And the Atlas
Copco service team is available all hours to keep the machines
up and running. In fact, we are expecting to finish drilling ahead
of schedule."
The
power of the rigs has also impressed at least one of the operators,
who said: "These drill rigs have the most drifter (rock drill)
power that I have seen. The machines are more complex than other
drill rigs but they drill a lot faster."
The
company added a second ROC F7 to their fleet in 1998. Their third
started work at the site in September.
The
ROC F7 is part of the new Power Generation range of surface drilling
rigs. Features include:
-Increased cabin ergonomics, with the operator controls placed
in the armrests
-Increased visibility during drilling and tramming, with a full-height
front window and
-Adjustable operator's seat and air conditioning.
Ken
Miller, one of the drillers operating the equipment, has high
praise for these ergonomic features, saying: "In 35 years
of operating drilling equipment, I've worked for a total of 14
months on the Atlas Copco ROC F7. It is definitely more operator-friendly
than any other rig I've operated. The cabin ergonomics are great."
|