|

|
When
the new 57 km-long St. Gotthard Base Tunnel through the
Swiss Alps is completed, passenger trains will travel through
its twin tunnels at up to 250 km per hour. And driving an
important access shaft at the project was completed at an
impressive speed, too.
|
Atlas
Copco drill rig's high-speed shaft drive
The
rate of progress at a major shaft-sinking project under the village
of Sedrun in Switzerland has amazed visiting engineers at the
site.
An
Atlas Copco shaft-sinking rig, equipped with six booms and COP
A15 pneumatic rock drills, has driven an 800 m-deep shaft down
to the planned route of the St. Gotthard Base Tunnel. The rig
was also used to provide the cover drilling, a method of keeping
the water away from the shaft.
 |
| How
access is obtained to the multi-function St Gotthard Base
Tunnel site. |
And an advance rate of 3-3.5 metres/day was achieved with the
rig. As a seven-day week was being worked on the project, this
amounted to some 100 metres/month when the rig was working continually.
After
solving the start-up problems, this high performance was maintained
throughout the rest of the project, which - including four months
of running-in time, preliminary work, rock reinforcement and final
finishing-off work - spans a period of 18 months.
The
consortium in charge of the construction of the Sedrun shaft consists
of the four Swiss contractors Murer AG Erstfeld, Zschokke Locher
AG Zuerich, Marti Tunnelbau AG Bern, CSC Impresa Costruzioni SA
Lugano, and the South African company Shaft Sinkers Inter- national
Ltd. Sandton.
The
completed Sedrun shaft, nicknamed "the multi-function site",
will be used for ventilation and maintenance. At its bottom, it
holds an emergency railway station and emergency rooms for the
train passengers.
Installed
at the site was a hoist, which will later be rebuilt to suit tunnelling
requirements. It lifts 10 tonne loads of rock in buckets at a
speed of 11 metres/ second - or 700 metres/minute.
In order to maintain the high rate of progress, forming of the
concrete lining was done in parallel with the general shaft sinking
operation. Several other operations were also carried out in the
shaft simultaneously.
 |
Star
performer in the Alps: The Atlas Copco six-boom shaft-sinking
rig in the 800 m-deep shaft down to the St. Gotthard Base
Tunnel.
|
A
platform provided five working decks. The lower Deck 5 was for
managing activities at the bottom of the shaft; the concrete forms
were mounted from Deck 3 for final lining in six-metre stages;
concrete was received through long pipes on Deck 2 to be remixed
and formed; and all supply lines were assembled on Deck 1.
Round
shafts
TShaft sinking is a speciality in South Africa because of the
many deep mines in the country. So it follows that Atlas Copco
South Africa has produced a series of drill rigs that are built
for this purpose.
The
rigs are designed for round shafts - the dominant choice and resemble
the spokes in an umbrella. The "spokes" are the booms
on the rig. There are three to nine booms and the rig works in
shaft diameters of 6-12 m. The air-powered COP A15 rock drills
fitted to the Atlas Copco rig at Sedrun were introduced in 1998
for shaft-sinking operations with water flushing of the drill
hole.
Impact
energy is 14 kW and the rock drill works with an air pressure
of 6-bar, requiring 300 litres of air per second. It is designed
for hole sizes of 51-102 mm and, at Sedrun, 51 mm was the choice
with penetration at 1.5 metres per minute.

The
hoist in the shaft: The muck bucket can take six cubic metres
of waste. |
The
contractor considers that the rock of schistose gneiss made blasting
difficult, as it required 2.9-3.6 kg of nitroglycerine-based explosive
per cubic metre in an area of 58 m2.
The
number of holes varied between 140 and 170 and they were normally
drilled to a depth of 3.5 m to give the required advance of 3.2
m. The holes were vertical and in a circle. The opening was achieved
by a parallel cut of three 102 mm holes placed in a triangle,
and these larger holes were drilled with a DTH hammer placed in
the centre of the rig. Each drilling period lasted about three
hours.

The
stage in the shaft: The platform structure has five decks
from which a variety of essential tasks are carried out. |
To
control the inflow of water, continual pre-injection was carried
out with 40 m-long holes drilled in a "trumpet" shape
downwards, a method of cover drilling.
Before
blasting took place, the entire shaft-sinking apparatus - called
"the stage" - had to be lifted 60 metres above the bottom
to avoid possible damage caused by flying rock.
Primary
reinforcement was carried out during a pause in the loading cycle
with 3 m-long Standard Swellex bolts and shotcrete. All the reinforcement
work took up to six hours and the total time invested in each
round was, at best, some 19 hours.
The
planned rhythm of one round per day was achieved - but it took
four months of running-in to reach the target.
A new standard
Robert Meier, Chief Site Supervisor, says: "The crew of some
140 operators consisted of several nationalities, so extra time
had to be allowed to get the crew to work like a team. This may
explain the low performance in the initial phase.
"But
producing the shaft, finished and lined, in 13 months is an achievement
which in all probability exceeds what most people would consider
possible."
The
shaft has been constructed by the specialist company Shaft Sinkers
of South Africa, and Senior Contracts Manager J.J. Kaalsen says
the project was a difficult but interesting challenge. He continues:
"It was pretty tough going in the beginning. There were so
many nationalities involved here that it was quite a feat to get
everything organised and set up.

A
job well done: The Senior Contracts Manager J.J. Kaalsen (left)
and Chief Site Supervisor Robert Meier say the going was tough
- but successful. |
"But
the Atlas Copco equipment made a great contribution and, in the
end everything was fine. The shaft-sinking rig worked well and
the project went according to plan.
"We think
the Sedrun project has set a new standard in the sinking of deep
shafts - and South African technology has shown the way."
Easing
the Alpine traffic flow
The St Gotthard
Pass in southern Switzerland has been used as a cross-Alpine
route since the 13th century and is now an important road
and rail link between central Europe and Italy.
The winding old road in the pass itself, 2,140 m above sea
level, is only open in the summertime. Beneath it, at an altitude
of 1,150 m, lies the 14 km-long St Gotthard Tunnel, through
which a railway opened in 1882 connects Luzern with Milan.
In 1980, at the same altitude, the 16 km-long St Gotthard
road tunnel - one of the longest in Europe - was opened to
accommodate 1,500 vehicles per hour.
High-speed
railways
Now the 57 km
St Gotthard Base Tunnel and the Lötschberg Base Tunnel,
35 km long, are being constructed at elevations of 550 m
and 750 m respectively as twin single-track, high-speed
railways. The deeper the tunnels are under the mountains,
the flatter the route becomes and the quicker the traffic
flows.
The new tunnels are part of the NEAT Alpine rail tunnel
project, which will eventually total around 170 km of track
- plus accesses like the one at Sedrun.
Truck traffic through Switzerland and the Alps is a growing
environmental problem and current rail routes operate at
full capacity. The EU-supported solution is to create faster
rail links and compel transit traffic to use them.
|
|