|
The
drillers' challenge at Venda Nova Boosting power for Portugal Drilling
contractors using Atlas Copco equipment are hard at work helping Portugal
to meet its future electricity needs.
The project includes a 2.8 km inlet tunnel, a 1.4 km discharge tunnel, one huge powerhouse cavern, a 625 m-long ventilation tunnel, a 1,210 m access tunnel, a 130 m water intake and two raisebored shafts of 415 and 110 metres. Important
project
A consortium
of three Portuguese companies has been formed to complete the civil
works of the Venda Nova upgrade - Somague, Moniz da Maia Serra &
Fortunato (MSF) and Mota & Companhia - and its managing director
Rui Manuel Ferreira Carrito, spoke about the rock conditions at the
site. The consortium is relying on equipment from Atlas Copco for most of the drilling and tunnelling work. For example, 3-4 m-long Swellex rock bolts are used in the tunnels. Rocket Boomer rigs are used for investigation and excavation drilling. Only 20 per cent of the tunnel requires a concrete lining as final support.
Time
savers He points out that the rigs can start the next job only when the current one is finished - and that's why Atlas Copco's ongoing maintenance support is so important. Right from the start, Atlas Copco has been providing training support for operators who were not skilled in working with the rigs, and Mr Carrito adds: "At the start of the project, a drilling round was taking five or six hours. But by the end, the time was down to less than two-and-a-half hours." The relationship between Somague and Atlas Copco goes back some 40 years. Mr Carrito comments: "We use a lot of Atlas Copco equipment. They are the main company in Portugal for drilling, mining and civil works and the only company that can provide a complete service from the beginning to the end of a project. "We also use their Swellex bolts, grout equipment, grouting tools, grout registers, drilling materials and rock drilling tools - for which we have a contract with Atlas Copco that guarantees a stock of all the materials we need on site. "We
can always ask for advice on what equipment to use, what kind of lifetime
figures we can expect from the rods, bits and shanks, how many metres
they should last in different conditions, and so forth."
Raising
expectations Drillcon Iberia Lda, a subsidiary of Drillcon AB of Sweden, was responsible for the operation. Primarily a cor e drilling company, Drillcon is involved in a number of different projects in Portugal and Spain where raiseboring is being done. Drillcon Iberia used a Robbins 73R raiseboring machine to develop the shaft. A Secoroc RRL 3.5 metre reamer was flown in from Australia especially for the job. A total of 18 new cutters were used on the reamer: nine 5-row cutters and nine 4-row cutters. The raisedrill was mounted on a concrete platform in the escape tunnel. The pilot hole was drilled down to the turbine hall and then the tunnel was reamed upwards, back to the escape tunnel. "The cutters performed perfectly," says Adriano Barros, Director General of Drillcon Iberia Lda. "The mucking was very easy. We put a little water in the bottom to alleviate the problem of dust and then used water pressure to assist with flushing the muck out during reaming." The rock at the site was very good, fairly hard granite of 170 MPa. The raise was completed in May, 2001 and the deviation on the hole was 40 cm for the entire length of 110 metres - less than 0.5 per cent - which is described as an "outstanding" performance on a shaft of that length and at that incline.
On-site
support "When
we were finished with the hole, Atlas Copco personnel were on hand to
show us how to re-service the reamer, maintain all the cutters and Drillcon Portugal is also involved in several other projects in Portugal where only Atlas Copco and Secoroc products are used. At the Somincor Mine, two Robbins raisedrills are permanently on-site, drilling approximately 2,500 m per year. For bench drilling, Somague has a ROC 748 drill rig and MSF has a ROC D5. Both were used extensively in the turbine hall, which represents almost a third of the project, and excavation was completed in September. Mr Carrito
says: "We used three phases. We had a drift on the top gallery
and two side drifts with a rock pillar in the middle for support. Steady
progress Meanwhile, with trained operators and reliable backup, the work is steadily progressing at three faces and averaging 80-90 m per heading and month with a site record of 110 m. The new plant and tunnel system is scheduled to be in operation in 2004. |
|
|
|
|
|