|
AIRLIFT
IN THE ANDES

Construction
of 6,200 metres of tunnels which will form part of the new Chinango
hydro power project in Peru is now complete.
Located in the
towering Andes mountain range east of the capital city Lima, the
three sites for the project were ideally suited for the production
of hydro power.
But they are in
a wild and remote area, inaccessible by road and subject to massive
downpours during the rainy season. An attempt was made to build
a supply road linking a small tunnel exit site, perched high on
a mountainside, to an existing track 180 metres below. After five
months, the project was abandoned when torrential rains and landslides
washed the new road away.
Difficult
option
Contractor Graña
y Montero was faced with the problem of getting all the heavy
construction equipment - drill rigs, construction vehicles, compressors
and rock drills - to the site quickly in order to meet the just-in-time
delivery requirements.
 |
| Difficult
to access: The Valves Chamber site is carved out of the side
of a mountain in the Peruvian Andes. Water pipes are hauled
up from the project's base camp, located some 180 metres below
the exit tunnel. |
The only option
available, although difficult and potentially hazardous because
of strong winds gusting through the narrow ravine leading up the
site, was to transport the equipment to the site by air, using
a specially-adapted crane helicopter.
Jorge Fernandez,
Head of Equipment for GyM, supervised a team of Atlas Copco technicians
who dismantled the equipment so that loads would be within the
safety limit of six tonnes per trip. Then the components were
carefully flown up to the site and reassembled to start their
various tasks.
Says Site Manager
César Vera: "The risky operation was a success, although
the setback delayed starting work on the tunnel by three months.
However, due to the excellent performance and availability of
the Atlas Copco equipment, we were able to recover the lost time.
So much so that we now expect this part of the project to be completed
a month ahead of schedule."
The USD 200 million
Chinango project in the Chanchamayo valley region of Peru is a
merger of two power stations which are under construction. The
40 MW Yanango plant is is scheduled for completion in mid-2000
and the 142 MW Chimay scheme will be ready a year later.
The completed
project will draw on the fast-running waters of the Tarma, Yanango
and Tulumayo rivers on the Atlantic watershed to generate a total
of 1,217 GwH per year. (See separate article).
Tunnelling work
started in April, 1998. Now, deep in the andesite rock, the headrace
tunnel has a cross-section of 9.8 m2 and is 5,045 metres long,
with secondary tunnels totalling over 1,000 metres.
Partners
again
The GyM project
team of Alfonso Gálvez, Operations Manager (Special Projects),
Site Manager César Vera and David Vásquez, Head
of Construction Works, chose Atlas Copco as the supplier of equipment
for the project. Their decision was based on the success of previous
partnerships between the two companies.
 |
| The
specially-adapted crane helicopter, ready for its mission.
It hoisted the equipment up to the Valves Chamber site without
mishap. |
Two contracts were
signed by the partners: The first was a service contract for the
maintenance of the Atlas Copco drill rigs, rock drills and vehicles
on the project, guaranteeing mechanical availability of 90%. The
second was a cost-per-drill-metre contract for rock drilling tools,
which included bit grinding.
Drilling
sites
Drilling was from
three headings - the Tarma Tunnel, the Yanango Access and the
Valves Chamber tunnel exit site, where the airlift took place.
Atlas Copco equipment is in operation at all three worksites.
At the Tarma Tunnel:
One Boomer H128 drill rig mounted with two COP 1238 rock drills,
one Scooptram 3.5 LHD vehicle, an MT-420B truck, six BBC 16 rock
drills and a Teroc 64 bit grinder.
At the Yanango
Access: One Raildrill 322 rig equipped with two COP 1838 rock
drills, four BBC 16 and three BBC 34 rock drills.
At the Valves
Chamber: One Boomer 282 unit mounted with two COP 1238 rock drills,
one Scooptram 3.5, one MT- 420B truck and eight BBC 16 rock drills.
Drill and blast
operations at the three worksites consisted of 46 holes per round,
using 14 ft-long rods and Teroc bit grinders. Drilling time was
between 60 and 90 minutes and four blasts per day were accomplished.
César Vera
is delighted with both the performance of the Atlas Copco equipment
and the success of the service and maintenance contracts.
He says: "I
want to emphasize that the high availability of the Atlas Copco
equipment was the key to success in this operation. We would not
have been able to perform major repairs at such an inaccessible
site but availability was 95% and only minor repairs were required.
"The service
and maintenance contracts also worked in a very positive way,
thanks to our close relationship with the Atlas Copco people.
There is mutual confidence and flexibility and we are always able
to come to an agreement on any differences that occur."
He concludes:
"We like working with companies that bring us solutions,
not problems. And Atlas Copco is a first-class example. We are
very happy with the price and quality of their services, their
quick response and support. In this difficult project, things
just had to work - and they did!"
|
Peru's
mighty power potential

The
road to San Ramon:
The Valves Chamber site is
high above the road and the river.
Harnessing the huge
energy potential created by Peru's lofty mountains and rushing
rivers has brought a big bonus to the country.
The current
total of installed electricity is 5,178 MW, which means
that energy supply now exceeds demand - leaving a comfortable
margin which guarantees a continued supply in emergencies.
By the next
century, the amount of electricity available stands to jump
by at least 15% while the estimated annual growth in demand
over the next five years is 5%.
And the
hydroelectric potential in Peru totals 74,700 MW. The national
electricity system uses only 2,500 MW - or some 3.3% of
that figure.
|
|