|
THE PERFECT SHAPE
OF THINGS TO COME
By
GUNNAR NORD, Senior Construction Advisor, Face Drilling and
Mechanized Bolting
An inaccurate contour,
or planned outline, of a tunnel following drilling and blasting
has long been a problem for tunnellers the world over.
The dilemma is
created by inexact drilling of the blast holes. This results in
overbreak, or excess rock, being blasted out, leaving irregularities
in the planned contour of the tunnel.
In simple terms,
the more overbreak, the more time and money is wasted, primarily
in mucking out. Transporting the excess rock - perhaps a considerable
distance - and restoring the tunnel to its planned smooth contour
with reinforcement and lining all means time lost.
Facts
and figures
The considerable
costs of overbreak can be illustrated by this hypothetical example:
A 70m2 two-lane road tunnel, 1 km long, is being built and, according
to the tender documents, only theoretical volumes of excavated
rock as well as secondary lining will be paid for. So-called geological
overbreak is compensated for and the perimeter of the tunnel is
typically 22 m.
 |
Gunnar
Nord: Dealing with overbreak brings big savings.
|
A reduced overbreak
of 10 cm resulting from more accurate drilling gives the contractor
these savings in Euros: Concrete secondary lining 2,200 m3 @ EUR
120/m3 = 264,000. Reduced mucking 2,200 m3 @ EUR 5/m3 =
11,000. Reduced shotcrete 200 m3 @ EUR 300/m3 = 60,000.
Reduced construction time 100 hours @ EUR 700/hr = 70,000.
Total savings: EUR 405,000.
These figures illustrate
the magnitude of the overbreak problem. However, placing holes
accurately and with a proper alignment is not new. It could be
achieved even in the era of hand-held drills, using short rounds.
But the problem was the amount of time it took.
Best
technique
As far back as
the mid-80s, an overbreak of less than 10 cm was recorded on drill-and-blast
sewage declines in Sydney, using both hand-held and mechanized
drilling.
During the same
period, on the Route 5 tunnel project in Hong Kong, mechanized
drilling operations employed the best technique then available
for accurate contours. It involved accurate setting out of the
tunnel face, TAS (Tunnel Angle System) for the alignment of the
feeds, an immediate monitoring of the profile - plus a bonus to
the rig operators. The results are shown in Figure 1.
More light at the
end of the tunnel came in recent years in the shape of a manual
contour control system introduced by the Norwegian company Bever.
It has been mounted on a large number of drill rigs - mainly Atlas
Copco Boomer units - and the operator is guided by a TV screen
in manually positioning the booms to achieve more accurate holes.
And in 1998, following
years of development, Atlas Copco launched its own contour control
system, which is being integrated into its new generation of rigs.
So far, it is operational only in manual mode but is due to be
available for robot drill rigs later this year.
 |
| Figure
1: Overbreak improvement at the Route 5 tunnelling project
in Hong Kong. |
Progress
at projects
The following four
examples of what can be achieved with Atlas Copco Boomer rigs
equipped with Bever control are from projects over the past five
years. The first two cases involve drilling with Robot Boomer
rigs.
The Henriksdal
sewage treatment plant, Stockholm, Sweden: The contractor
wanted very high drilling standards, although there was no secondary
concrete lining in the design. The length of the rounds was 5
m and the size of the opening some 80 m2. The rock was hard crystalline
granites and gneiss, which was not expected to cause a drill steel
deviation problem.
The skill of the
operators was rated highly, conditions were favourable - but incentives
were not strong, as there were no savings to be made on concrete.
The average overbreak was 14 cm outside the collaring line and
the distribution is shown in Figure 2.
The Escalette
road tunnel project in southern France: The two tunnel tubes
were to be concrete lined with a strong incentive to keep overbreak
down. Excavated sedimentary material was dominated by limestone,
which had a clear bedding with a gentle dip.
Tunnels were some
700 m long with an excavated cross-section of about 70m2. Rounds
were 4 m or less, if ground conditions were poor. Tunnel sections
with geological overbreak were excluded from the study.
Results, shown
in Figure 2, were very similar to Henriksdal - although conditions
were quite different - and showed what can be achieved by the
equipment and good operators in moderate-size tunnels without
difficult geological conditions.
The Mitholz
tunnel in Switzerland: This adit tunnel to the Lötschberg-Basistunnel
showed the most encouraging results on overbreak using the Bever
control. The 1.5 km adit has an excavated section of 66 m2 and
the rock has so far been limestone and shale. Normally, 4 m rounds
were drilled and the pull was 3.8 m. In the 0.6 m-spaced perimeter
holes, smooth blasting explosives were used with electronic detonators.
The drill rig was
a Rocket Boomer 353 S and the contractor wanted as little overbreak
as possible as he had to pay SFr 300 for every cubic metre of
it that was more than 6 cm outside the theoretical line. Over
the entire tunnel length, this meant the penalty for every extra
cm of average overbreak amounted to SFr 93,000.
For the first 100-200
m of the tunnel, average overbreak was 25 cm. But by the time
work had progressed to 700 m, it had come down to 10 cm as the
skill of the drilling crews improved.
 |
| Figure
2: Similar overbreak advances at the Henriksdal and Escalette
projects. |
Boliden's
Garpenberg Norra Mine, Sweden: An Atlas Copco Rocket Boomer
352 S has been used on the latest section of the ramp tunnel and
overbreak was reduced from more than 20% to 9%, or an average
of 15 cm. This resulted in a reduction of the muck volume of 3
m3 per lineal metre of tunnel and savings on transport from a
depth of 800 to 1,000 metres.
According to the
mine management, the savings achieved in one year paid for the
extra cost of improving drilling operations at the mine.
The reasons for
these excellent results include young and dedicated rig operators
and the fact that the rock itself does not generate any noticeable
overbreak.
Important
factors
So what are the
main factors in reducing overbreak?
First, the
ambition of the site managers and operators is extremely important.
Close monitoring of the tunnel face is a must in order to register
undue overbreak and take counter measures - and a small bonus
to the people involved can lead to great results.
Geological
conditions can have a great effect on hole direction. The drill
string has a tendency to deviate perpendicular to the foliation
in anisotropic rock like phyllite, schist and gneiss. The problem
is more acute in surface drilling when far longer drill rods are
used. And a high frequency of jointsets in the rock can also influence
the drilling direction.
Blasting
is extremely important, and employing the smooth blasting technique
with electronic detonators in the periphery holes can contribute
greatly to a smooth tunnel contour.
Tunnel size
affects drilling accuracy. When booms and feeds are extended to
the full, they are not so rigid and deflections can occur. Exact
computerized compensation is not easy to achieve - and the further
out the booms are, the greater the collaring and orientation errors
can be.
Alignment
of the feed is critical at the start of drilling and a tunnel
face which is not orientated perpendicular to the drill rod may
cause bending and an inaccurate starting point. Low feed force
and reduced impact at the start saves drill tool wear and, after
that, feed force should be just enough to maintain tight joints
without bending the rod and risking deviation.
Fast and accurate
drilling requires dedication, experience and reliable, state-of-the-art
drill rigs. With these prerequisites, there are not many projects
where the economic advantages of contour control can be ignored.
For
more information please contact gunnar.nord@atlascopco.com |